The North Carolina Court of Appeals issued a decision addressing the statutory requirements for claims of lien on real property. The June 2026 decision emphasizes that the dates stated in a claim of lien – particularly the first and last dates of furnishing labor or materials – must be accurate for the lien to be enforceable.
In K. Lee Builders, Inc. v. Barnes, the Court held that a claim of lien containing incorrect "first furnishing" and "last furnishing" dates did not substantially comply with North Carolina's lien statute, N.C.G.S. § 44A-12, and was therefore invalid and unenforceable. Although the contractor prevailed on its breach-of-contract claim at trial and obtained a judgment exceeding $53,000, the Court concluded that the contractor could not recover from the bond posted to discharge the lien because the lien itself was defective.
What Happened
K. Lee Builders, a licensed general contractor, entered into a contract with a homeowner, "Barnes," to build a home in Henderson, North Carolina. After a payment dispute arose, the contractor filed a claim of lien. The claim of lien listed September 5, 2022, as the date labor was first furnished, while the evidence showed that construction activity began on November 2, 2022. The claim also listed August 25, 2023, as the date labor was last furnished, although work continued until at least September 13, 2023. The homeowner posted a cash bond to discharge the lien from the property.
The homeowner moved for summary judgment on the lien enforcement claim, arguing that the inaccurate first- and last-furnishing dates were material defects. The trial court initially granted summary judgment in open court but later determined that the claim of lien substantially complied with the statute.
The case proceeded to trial. The jury found that the homeowner breached the contract and awarded the contractor damages.
What the Court Decided
1. Inaccurate Dates Rendered the Lien Unenforceable
The Court of Appeals held that inaccurate first-furnishing and last-furnishing dates were material defects in the claim of lien. North Carolina law requires a claim of lien to state both the date labor or materials were first furnished and the date they were last furnished. The Court explained that these dates serve important public-notice functions:
- The first-furnishing date determines lien priority because a valid lien relates back to the date work first began.
- The last-furnishing date allows property owners, lenders, and title examiners to assess whether the lien was filed within the statutory deadline.
The Court emphasized several key points:
- A claim of lien cannot be amended after it is filed. Under N.C.G.S. § 44A-12(d), the information included in the recorded claim controls. The statute does not provide a procedure for correcting a filed claim of lien by amendment.
- Lack of actual prejudice did not cure the defect. Although the parties were aware of the relevant dates, the Court held that substantial compliance requires accurate information on the face of the claim. The analysis focused on the statute's public-notice function, not only on whether the parties to the dispute were misled.
- The errors were not treated as obvious scrivener's errors. The Court distinguished mistakes that are apparent from the face of the document and easily reconciled, such as an impossible date sequence, from inaccurate but facially plausible dates. Because the dates here appeared plausible on the face of the lien, they were not excused as clerical mistakes.
2. An Invalid Lien Did Not Support Recovery from the Bond
The Court also held that, because the claim of lien was invalid, the contractor could not recover from the cash bond posted by the homeowner. Under N.C.G.S. § 44A-16, a bond posted to discharge a lien serves as a substitute for the property while the lien claim is resolved.
Because the lien was unenforceable, the Court concluded that the bond funds should be released back to the homeowner.
Important: The contractor retained its breach-of-contract judgment, but the judgment was no longer secured by the bond. As a result, collection would proceed through ordinary post-judgment collection methods rather than through enforcement against the lien discharge bond.
Practical Takeaways
The decision provides guidance for contractors, property owners, lenders, and others who rely on the information contained in recorded lien filings. Key points include:
- Maintain accurate, contemporaneous project records. Parties preparing or reviewing lien filings should document the actual first and last dates of furnishing labor or materials through project logs, dated photographs, delivery records, invoices, correspondence, and other reliable records.
- Verify lien dates before filing or responding. The dates listed in a claim of lien should be checked against project records. Property owners and other interested parties should also consider whether the dates stated in a lien are supported by the project history.
- Recognize the limits on correcting filed lien claims. North Carolina law does not provide for amendment of a claim of lien after it is filed. If an error is discovered, the available options and timing consequences should be evaluated promptly, including whether a new claim can be filed within the statutory deadline.
- Do not assume minor date discrepancies will be overlooked. The Court's analysis indicates that facially plausible but inaccurate dates may be treated as material, even if the opposing party was not actually misled.
- Consider legal review before filing or challenging a claim of lien. Because lien rights are statutory and timing-sensitive, legal review may help identify defects, preserve available remedies, and assess whether a lien or bond claim is enforceable.
- Understand the separate roles of lien rights and contract claims. A party may prevail on a contract claim while still losing the security associated with a lien if the lien does not comply with statutory requirements. The enforceability of the lien and the merits of the underlying contract dispute are related but distinct issues.
Contact Us
If you have questions about this decision, lien rights, or the preparation, review, enforcement, or challenge of a claim of lien, please contact our Construction Law Practice Group.